Construction, Social & Infrastructure Projects, Trading and Manufacturing

Email:  info@haro-group.com


Manufacturing

MEAT PROCESSING FACTORY

Gulf Meat Products FZC, Factory, UAE

As a private venture, during 2011-12, the HARO group built a Meat Processing Factory in Hamriyah Free Zone, UAE.  The group operated the factory producing burgers, sausages and canned meat items.


The factory had a monthly production capacity of:


   a.  Sausages - 350 tonne 

   b.  Burgers - 100 tonne

   c.  Canned items - 100 tonne    


The factory was a complete turn-key project with an overall plot area of 5,000m2 and building areas of approximately 2,600m2. The main features of the factory are:

   a.    Production and Storage area - 1,600m2
   b.    Office and Utility buildings - 1,000m2

   c.    Separate water and sewage system

   d.    Electrical connection to the city grid and
          an automated generator backup system

Working area of 1,850 m2 (production facilities, cold room, freezer, chiller and delivery docks) and 400m2 office area.     

The Group also developed its' 'own-label' high end, quality meat products:




  
  

UPVC DOORS & WINDOWS FACTORY

Winhouse Factory, Kabul, Afghanistan

The Winhouse factory was build by the HARO Group during 2002-2003 in Kabul, Afghanistan, on the same site as the HARO Construction Afghanistan Ltd site, on Jalalabad Road,in Kabul.

The factory was the largest and most modern UPVC factory in Afghanistan using the latest equipment technology, including Elumatec machines from Germany. 

The company supplied doors and windows throughout the country and the Group used the doors and windows on all relevant construction projects in Afghanistan.

Winhouse used the unique Winkhouse profile and operating system, allowing 3-way opening.

Tha Winhouse factory comprised:

   a.  1,000 m2 Production Area
   b.  2 x Offices
   c.  Material Store

  
  
        

LIMESTONE PRODUCTION FACTORY

XELLA/HARO GZG, Kosovo

The silicate limestone factory was built as a Joint Venture between XELLA GGZ and HARO Construction Ltd, during 2005-2007.

The factory was able to produce 40 Million stones per year.    The stones were used for the reconstruction of Kosovo, post-conflict and also shipped to construction sites throughout europe.